Security of Payment Act NSW

Security of Payment Act NSW: payment claims, schedules and deadlines

The Building and Construction Industry Security of Payment Act 1999 is how builders, trades and suppliers in NSW get paid on time. It sets a monthly right to claim, short deadlines to respond, and a fast adjudication process when payment does not arrive. This guide puts every deadline in one table and walks through making a claim, answering one, and what to do when you are not paid.

By Tylar Edwards, nine years on the engineering and contracts side of $50M-$500M Australian construction projects before founding laikodev. Updated .

On this page
  1. Every deadline in one table
  2. Who the Act covers
  3. How to make a valid payment claim
  4. If you receive a payment claim
  5. If you are not paid
  6. Where the admin goes wrong, and where AI helps
  7. Sources and limits
  8. Common questions

Every deadline in one table

Most disputes under the Act are won or lost on a date, not on the work. These are the maximum times the Act allows; your contract can set shorter ones, never longer, so check it first.

StepDeadlineSection
Respond to a payment claim with a payment schedule10 business days after receiving the claim, or earlier if the contract says sos 14
Principal pays a head contractor15 business days after the claims 11
Head contractor pays a subcontractor20 business days after the claims 11
Head contractor pays a subcontractor on related residential work10 business days after the claims 11
Apply for adjudication after receiving a schedule for less than claimed10 business days after receiving the schedules 17
Apply for adjudication when a scheduled amount is not paid20 business days after the due dates 17
No schedule and no payment: notice of intention to apply for adjudication20 business days after the due dates 17
No schedule: respondent's last chance to provide one5 business days after receiving the notice of intentions 17
No schedule: apply for adjudication10 business days after that 5 day window endss 17
Respondent lodges an adjudication response5 business days after receiving the application, or 2 after the adjudicator accepts, whichever is laters 20
Pay an adjudicated amount5 business days after the decisions 23
Notice before suspending work for non-payment2 business days, in writings 27

Deadlines are business days. Count from the day the document is received, and keep proof of when that was.

Who the Act covers

Anyone carrying out construction work, or supplying related goods and services, in NSW under a construction contract. The contract can be written, verbal or informal, and the right to progress payments applies even if the contract says there are none.

Residential owner-occupier contracts entered into from 1 March 2021 are covered. NSW guidance lists exceptions where you contract directly with a person who lives or intends to live in the home: residential building work under $5,000 in total, and electrical wiring, plumbing, drainage and gasfitting, and air-conditioning and refrigeration work. The Act also does not help a claimant company that is in liquidation.

How to make a valid payment claim

You can claim once a month: from the last day of the month in which work first started, then from the last day of each following month, or from an earlier date the contract sets. A claim can roll in unpaid amounts from earlier months, and on contracts signed from 21 October 2019 you can claim from the date the contract is terminated.

A claim that holds up:

  • Is in writing and states the amount you say is due.
  • Identifies the work, goods or services it covers, ideally with a work statement, photos, dockets or completion certificates.
  • Says it is made under the Act. Use: "This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 NSW."
  • Is served the way the contract allows, in person, by post or another agreed method, and you record the date it was received.
  • Includes a supporting statement if you are a head contractor claiming from the principal, declaring your subcontractors have been paid what is due.

If you receive a payment claim

If you will not pay the full amount, send a payment schedule so it reaches the claimant within 10 business days. It must be in writing, identify the claim, state the amount you will pay (which can be "Nil"), and give every reason for paying less. Attach your valuation of anything withheld.

Treat the schedule as your whole defence. A respondent cannot raise reasons in adjudication that were not in the schedule, and missing the deadline makes you liable for the full claim with no contract defences or cross-claims.

If you are not paid

You have four levers, and they can be used together:

  • Adjudication. Lodge with an authorised nominating authority of your choice within the deadlines above, serving a copy on the respondent. The respondent must pay an adjudicated amount within 5 business days.
  • Enforce the decision as a judgment. Get an adjudication certificate and file it with an affidavit in court; it becomes a judgment debt without the dispute being reheard.
  • Suspend work on 2 business days' written notice that says it is given under the Act.
  • Recover the debt in court, where a respondent who gave no schedule cannot raise contract defences.

Adjudication is "pay now, argue later": the payment is not final, and either side can still pursue its full contractual rights afterwards.

Where the admin goes wrong, and where AI helps

The Act rewards whoever keeps better records and counts days correctly. Small builders and subcontractors usually lose rights the same few ways: a claim date missed because the month got away, a claim that does not clearly identify the work, a payment schedule that arrives on day 11, or a supporting statement forgotten in the rush to get a claim out.

That is the kind of work an AI agent handles well. A claims agent can draft each month's claim from the contract schedule, site diary and approved variations, add the statutory wording and supporting statement, and count the business days on every claim you send or receive, stopping for your sign-off before anything goes out. See AI agents for construction for how the claims, variations and compliance agents work together, or the AI for construction guide.

Sources and limits

This guide follows the NSW Government's security of payment guidance and the section numbers it cites, checked on 20 November 2026. It is general information, not legal advice. The law changes, and court decisions refine how it applies; read the current Act on the NSW legislation website and get advice from a construction lawyer before relying on a deadline in a live dispute.

Common questions

How long should a subcontractor wait to be paid in NSW?
No more than 20 business days after making a payment claim, or 10 business days for related residential work, unless the contract sets an earlier date. A contract can shorten these times but cannot lengthen them, and pay-when-paid clauses are prohibited.
What does the Security of Payment Act apply to?
Construction work, and goods and services related to it, carried out in NSW under a construction contract, whether that contract is written, verbal or informal. It gives anyone doing that work the right to progress payments, even if the contract says there are none. Since 1 March 2021 it also covers contracts with residential owner-occupiers, with some exceptions for small and trade-specific jobs.
What happens if I do not respond to a payment claim?
You become liable for the full amount claimed. If the claimant goes to adjudication or court, you cannot raise defences under the contract or cross-claims. If you dispute any part of a claim, send a payment schedule with all your reasons within 10 business days.
Does a payment claim have to say it is made under the Act?
NSW Government guidance requires the statement on subcontractor claims connected with a residential construction contract, and some of its pages describe it as required on all claims. Including the sentence "This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 NSW" costs nothing and removes the argument.
What is a supporting statement?
A declaration a head contractor must give with a payment claim to the principal, confirming all payments due to its subcontractors have been paid. NSW guidance lists a maximum penalty of $22,000 for not providing one, and $22,000 and or three months' imprisonment for a knowingly false statement.
Can I stop work if I am not paid?
Yes, after giving 2 business days' written notice, when the claimed amount is unpaid by the due date with no schedule, a scheduled amount is unpaid by the due date, or an adjudicated amount is unpaid within 5 business days of the decision. You are not liable for losses caused by the suspension, and you must resume within 3 business days of being paid in full.

Fully managed

Start with a free intake call

Tell us the job eating your week and book a free 30-minute intake call. We map it with you, then send a written scope with a fixed price. You only pay if you choose to go ahead. First workflow live within 7 days of your deposit, or your deposit back. Every agent and tool we build is fully managed by us, monitored 24/7, with a 1-hour response to urgent issues.

Book a free intake call