Free RAMS template: risk assessment and method statement builder

The RAMS agent is a free RAMS template you fill in online and print or save as a PDF, with a briefing record for the team to sign. It follows HSE guidance, and the guide below covers what a RAMS is, when the law requires one, and how to write the risk assessment and the method statement.

Free · no login · 5 drafts a day

By Tylar Edwards, nine years on the engineering and contracts side of $50M-$500M construction projects before founding laikodev. Updated .

On this page
  1. Build your RAMS with the RAMS agent
  2. What a RAMS is
  3. Is a RAMS a legal requirement?
  4. How to write the risk assessment
  5. Choosing controls
  6. How to write the method statement
  7. Using and reviewing a RAMS
  8. Keeping RAMS current across jobs
  9. Sources and limits
  10. Common questions

Build your RAMS with the RAMS agent

Describe the job in a sentence and the RAMS agent drafts the risk assessment, a step-by-step method statement, the PPE, the plant, the competence the work needs and the emergency arrangements. Add your website and it fills in your company name, phone and logo. You then check every line against the site, add names and dates, and print it with a briefing record for the team to sign.

RAMS agent

Describe the job in one line and the agent drafts your risk assessment and method statement, ready to brief the team.

  • Free
  • Drafted from one line about the job
  • Print or save as PDF

What a RAMS is

RAMS stands for risk assessment and method statement. The risk assessment records the hazards of the work, who might be harmed and how, and what you are doing to control the risks. The method statement takes those conclusions and describes, in a logical sequence, exactly how the job is to be carried out safely, including all the control measures.

HSE describes a method statement as an effective and practical way to plan, manage and monitor construction work, and to tell the people doing it how the work should be done and what precautions to take. It is most useful for higher-risk, complex or unusual work, such as steel and formwork erection, demolition or the use of hazardous substances, and HSE calls it the common way to manage roof work.

How to write the risk assessment

HSE breaks managing risk into five steps:

  1. Identify the hazards. Think about how the work is done, the plant, equipment and substances used, and the state of the site. Look back at accident and ill health records, and include non-routine work such as maintenance and cleaning, and health hazards such as manual handling and chemicals.
  2. Assess the risks. Decide who might be harmed and how, including other trades, visitors and the public, what you are already doing, and what more is needed.
  3. Control the risks. Do everything reasonably practicable to protect people from harm.
  4. Record your findings: the hazards, who might be harmed and how, and what you are doing to control the risks.
  5. Review the controls to make sure they are working.

Talk to the people doing the work, and think about workers with particular needs, such as young workers, new or expectant mothers and people with disabilities.

Choosing controls

Start by asking whether you can get rid of the hazard altogether. If not, HSE suggests, in turn:

  1. redesign the job
  2. replace the materials, machinery or process with something less dangerous
  3. organise the work to reduce exposure
  4. put in place the practical measures needed to work safely
  5. provide personal protective equipment and make sure it is worn.

This follows the general principles of prevention in the 1999 Regulations, which put avoiding the risk first and give collective protection, such as edge protection, priority over individual protection, such as a harness. The RAMS agent lists controls in that order, so PPE is never the only thing between the team and the hazard.

How to write the method statement

  • Set the job out in the order it happens, from arrival and set-up to clear-up, with the controls for each step written into it.
  • Draw on the risk assessment for the hazards and how each one is controlled.
  • Cover your health and safety organisation, the training people need, and the arrangements for serious or imminent danger.
  • Say how the work affects other contractors on site. It also helps the principal contractor build the construction phase plan.
  • Use diagrams where they make the method clearer; HSE notes the most effective method statements often do.
  • Check on site that the method is actually being followed. HSE calls this a useful monitoring tool.

Using and reviewing a RAMS

  • Brief the team on the RAMS before work starts, and keep a record that each person has been briefed.
  • Review it if the controls may no longer be working, or when the people, process, substances or equipment change.
  • Review it when workers spot a problem, and after any accident or near miss.
  • A repeated job will have a similar RAMS each time, but revise it for each job when circumstances change markedly.

HSE warns against copying an example and putting your company name on it: that does not satisfy the law or protect anyone. Treat a drafted RAMS, including one from the RAMS agent, as a starting point to check against the actual job.

Keeping RAMS current across jobs

For a contractor the hard part is rarely one RAMS. It is producing one for every job and tender, getting the team briefed and signed, and keeping them current as jobs change. That is the kind of admin the agents in our AI agents for construction take on, starting with a free intake call. For the Australian and US versions of this document, see the free SWMS template and the free JSA template.

Sources and limits

This page and template follow HSE's guidance on managing risks and risk assessment and its risk assessment template, HSE's construction guidance on method statements, and the general principles of prevention in the Management of Health and Safety at Work Regulations 1999, all read on 23 November 2026. A completed template does not by itself make work safe or compliant: it has to reflect your actual job, site and team, and be followed.

Common questions

What is the difference between a risk assessment and a method statement?
The risk assessment identifies the hazards of the work, who might be harmed and how, and the controls. The method statement then sets out, in a logical sequence, exactly how the job will be done safely, including those controls. Together they are known as RAMS.
Is a RAMS a legal requirement?
The risk assessment is: the Management of Health and Safety at Work Regulations 1999 require employers to assess the risks, and to record the significant findings if they employ five or more people. HSE says method statements are not required by law for most work, but the arrangements for demolition, dismantling or structural alteration must be recorded in writing before work begins, usually in a method statement. Clients and principal contractors often ask for RAMS before you start, so check your contract and site rules.
Who should write a RAMS?
HSE says you can assess the risks yourself or appoint a competent person to help. Involve the people who do the work, as they usually have good ideas, and make sure the method is one they can actually follow on site.
How often should a RAMS be reviewed?
Review it if the controls may no longer be working, when the work, people, materials or equipment change, and after an accident, a near miss or a problem the team reports. If a similar job is repeated the method statement will be similar each time, but revise it whenever circumstances change markedly.
How does a RAMS compare with a SWMS or a JSA?
They cover the same ground under different rules. A SWMS (safe work method statement) is the Australian document for high risk construction work, and a JSA (job safety analysis) is the usual US form. In the UK, the RAMS is how contractors record the risk assessment and the safe system of work for a job.
Is this RAMS template free?
Yes, including up to five AI drafts a day. The draft is saved in your own browser. When you ask the agent to draft it, your job description, site and website are sent to us, and the job description and site to Anthropic's Claude model to write the draft; none of it is stored. Then print it or save it as a PDF.

Fully managed

Start with a free intake call

Tell us the job eating your week and book a free 30-minute intake call. We map it with you, then send a written scope with a fixed price. You only pay if you choose to go ahead. First workflow live within 7 days of your deposit, or your deposit back. Every agent and tool we build is fully managed by us, monitored 24/7, with a 1-hour response to urgent issues.